Grange Castle Power Plant, Co.Dublin

Ampromech were engaged in the M&E design as part of an overall design and build team for a new back-up power plant in Grange Castle Business Park designed to account/compensate for possible fluctuations in the grid as a result of the developing integration of renewable energies. The plant is designed to act as a peaking plant, feeding a total of 111MW of electrical energy into the Irish grid to help cover periods of high demand.
Power Generation Engineers
Case studies

Project GCPP:

The overall project involved the provision of the following:
6 no. engine cells each containing 1 no. 20MW gas turbine engine and vendor skids.
Utility spaces for LV distribution
Compressed air and LPHW boilers
Diesel fuel oil, urea and lube oil storage facilities
MV substation
Security, warehouse, and pump house buildings
Vortex fire supression, foam storage and sprinkler tank, and fire pump enlosures.
Engineer Power Generation
Case studies

Project Specific Design Services:

The key aspects of the APM role on this project were as follows:
Design of fuel handling systems to ensure fuel maintained in top condition over an extended time period.
Design of a fuel oil and ancillary chemical storage facility, containing two million litres of diesel fuel oil in 9 storage tanks, Lube Oil and UREA in an EPA compliant secondary storage facility
Design of a high pressure gas system including duty standby gas filtration, pressure reduction and associated controls and monitoring.
Design of all site utilities including compressed air (service and control), water, LPHW, low pressure gas.
Engineer Power Generation
Power Generation Image
Design of Ventilation systems to allow adequate airflow, heating and cooling of engine bay including dilution air to limit extent of hazardous areas.

Completion of HAZOP, Hazardous Area Classification and Computational Fluid Dynamics studies to support the design.

Integrated design of vendor supplied P&IDs and systems, including high pressure air systems, and hand-in-hand coordination with other disciplines.
3D modelling of all process & utility equipment and piping to LOD 300, providing adequate access to all components in a particularly tight site.
Case studies

Project GCPP:

End Client:

SDCL

Project Value (€):

150M

APM Client:

Collen Construction

M&E Contract Value (€):

45M

Project Type:

EPCM Contract

Duration:

30 Months

Location:

Grangecastle, Co. Dublin

Who we work with

Trusted By Leading Companies

KTA Logo
Collen Logo
SDCL Logo
Clifton Scannell Emerson Associates Logo
Lynskey Engineering Ltd Logo
MAN Energy Solutions Logo
CJK Logo
What we’ve done

See More Case Studies

PHARMA

Pharma Projects

Various Locations
Food & Beverage

Keurig Dr.Pepper

Newbridge, Co. Kildare
Data Centre

Project Iris

Holland

Embark on a journey towards innovation!

Connect with our expert team today. We’re here to answer your questions and guide you through the engineering solutions you need.